MCORE Project Construction Work to Restart on March 5

2/27/2018

0 Comments

 
On Monday, March 5 work will begin on the 2018 phases of the MCORE Project including:
  • Construction on Third St. - north and south of Green St.
  • Green St. will remain open to vehicular traffic, however work will occur on the sidewalks on Green St. between Second St. and Third St.
  • Landscaping and other miscellaneous work will occur along Green St. between Neil St. and Second St.
  • Construction will also begin at the intersection of White Street and Fourth Street. There will be a closure of the east half of the intersection, allowing for only one-way traffic southbound.  After the east half is complete, construction will occur on the west half.
Upcoming work scheduled to begin May 14 (after Commencement). More details will follow:
  • Construction on Green St. from Third St. to Fourth St.
  • Construction on Wright St. from White St. to Springfield Ave.
The City of Champaign, appreciates the cooperation and patience of property owners, residents, and visitors of the Campustown area during this important project.
0 Comments

MCORE Project 1 (Urbana) Update

2/21/2018

0 Comments

 
Traffic signal work at the intersection of Lincoln Ave. and Green St. began today. The work is expected to last through Friday, February 23, 2018 - weather dependent. The traffic signals are being replaced. During the daytime, the intersection will act as a four-way stop controlled intersection. Message boards will be installed north and south of the intersection alerting motorists of the stop signs. Delays to motorists near the intersection can be expected while this work is occurring. The traffic signals are expected to be operational each evening. Pedestrian access through this location will be maintained at all times. 
Picture
0 Comments

    Archives

    January 2021
    July 2020
    May 2020
    March 2020
    September 2019
    August 2019
    April 2019
    March 2019
    February 2019
    September 2018
    August 2018
    April 2018
    March 2018
    February 2018
    December 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017

    Categories

    All
    Armory Avenue
    Busey Avenue
    Chalmers Street
    Champaign
    CUMTD
    Daniel Street
    Florida Avenue
    Goodwin Avenue
    Green Street
    John Street
    Lincoln Avenue
    MCORE Project 1
    MCORE Project 2
    MCORE Project 3
    MCORE Project 4
    MCORE Project 5
    Sixth Street
    Urbana
    White Street
    Wright Street

    RSS Feed

    Additional Project Information

    University of Illinois
    City of Urbana
    CU MTD


About the Project
Project Schedule

Project Team
Document Center
Frequently Asked Questions
Photo Gallery
MCORE Projects
Green Street - Champaign
White Street - Champaign
Wright/Armory Street - Champaign
Green Street - University District
Green Street - Urbana
Interact with Us
Newsletter Subscription
Social Media