Project Schedule


Picture
Project Development Phase (All Projects)
  • February 2015 - Begin Preliminary Design
  • October 2015 – Complete Preliminary Design

Final Design Phase (Projects 1, 2 and 3)
  • March 2015 - Begin Final Design 
  • May 2016 – Complete Final Design
  • July 2016 – IDOT Bid Letting
  • August 2016 – IDOT Bid Rejection Due to Bids Over Budget
  • November 2016 – IDOT Bid (Rebid) Letting
  • December 2016 - IDOT Bid Acceptance 

Construction Phase (Projects 1, 2 and 3)
  • January 2017 – Award Construction Contract
  • March 2017 – Begin Construction
  • December 2018 - Complete Construction

Final Design Phase (Projects 4 and 5)
  • February 2017 - Begin Final Design Project 4
  • December 2018 - Begin Final Design Project 5 
  • October 2018 – Complete Final Design
  • November 2018 – Bid Letting

Construction Phase (Project 4)
  • January 2019 – Award Construction Contract
  • March 2019– Begin Construction
  • December 2020 - Complete Construction

Construction Phase (Project 5)
  • January 2020 – Award Construction Contract
  • March 2020– Begin Construction
  • December 2020 - Complete Construction

* All dates subject to change
About the Project
Project Schedule

Project Team
Document Center
Frequently Asked Questions
Photo Gallery
MCORE Projects
Green Street - Champaign
White Street - Champaign
Wright/Armory Street - Champaign
Green Street - University District
Green Street - Urbana
Interact with Us
Newsletter Subscription
Social Media